Substation Scout

MISO request N001

MISO queue ID N001

Queue request N001 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW wind project in Benton County, IN, according to Berkeley Lab’s queue data file. The filing names Goodland 138 / Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of October 1, 2008.

Queue IDN001
Project nameNot reported
Status (as published)Operational
SubstationGoodland 138 / Substation
Point of interconnectionGoodland 138 / 69 kV Substation
CountyBenton
StateIN
Voltage69 kV
Capacity100 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2008-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Benton, IN: 16 requests in the MISO queue, 8 active totaling 960 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterN001 N001
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2003-01-30
Interconnection agreement date2005-10-18
Operational date2008-10-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first