MISO request J815
MISO queue ID J815
Queue request J815 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW solar project in Christian County, IL, according to Berkeley Lab’s queue data file. The filing names Taylorville South-Austin (formerly Pawnee) Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 28, 2022.
| Queue ID | J815 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Taylorville South-Austin (formerly Pawnee) Line |
| Point of interconnection | Taylorville South-Austin (formerly Pawnee)138kV Line |
| County | Christian |
| State | IL |
| Voltage | 138 kV |
| Capacity | 250 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2022-10-28 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Christian, IL: 16 requests in the MISO queue, 8 active totaling 2,040 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | AMEREN ILLINOIS |
|---|---|
| Cluster | DPP-2017-AUG Central |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Construction |
| Study phase (as the queue printed it) | Study Phase: GIA; Post GIA Status: Under Construction |
| Queue date | 2017-06-16 |
| Interconnection agreement date | 2020-04-16 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.