Queue request J793 was listed in the MISO interconnection queue at the end of 2025 as a 1,175 MW gas project in St. Clair County, MI, according to Berkeley Lab’s queue data file. The filing names Belle River - Fitz #2 Line Tap as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of May 14, 2021.
| Queue ID | J793 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Belle River - Fitz #2 Line Tap |
| Point of interconnection | Belle River - Fitz #2 345 kV Line Tap |
| County | St. Clair |
| State | MI |
| Voltage | 345 kV |
| Capacity | 1,175 MW |
| Resource (as published) | Gas |
| Resource category | Gas (normalized for filtering) |
| Proposed online date | 2021-05-14 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
St. Clair, MI: 17 requests in the MISO queue, 7 active totaling 2,427 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ITC MIDWEST |
|---|---|
| Cluster | DPP-2017-AUG East (ITC) |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Study Phase: GIA; Post GIA Status: In Service |
| Queue date | 2017-06-16 |
| Interconnection agreement date | 2020-10-26 |
| Operational date | 2021-05-14 |