Substation Scout

MISO request J646

MISO queue ID J646

Queue request J646 was listed in the MISO interconnection queue at the end of 2025 as a 1.6 MW project in Macomb County, MI, according to Berkeley Lab’s queue data file. The filing names Carbon - connecting to ITC at Jewel, St-Clair and Spokane substations as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of July 1, 2010.

Queue IDJ646
Project nameNot reported
Status (as published)Active
SubstationCarbon - connecting to ITC at Jewel, St-Clair and Spokane substations
Point of interconnectionCarbon - connecting to ITC at Jewel, St-Clair and Spokane substations
CountyMacomb
StateMI
VoltageNot reported
Capacity1.6 MW
Resource (as published)Other
Resource categoryOther (normalized for filtering)
Proposed online date2010-07-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Macomb, MI: 7 requests in the MISO queue, 6 active totaling 282.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
ClusterDPP-2017-FEB East (ITC)
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2016-06-16
Interconnection agreement date2019-04-26

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first