MISO request J515
MISO queue ID J515
Queue request J515 was listed in the MISO interconnection queue at the end of 2025 as a 400 MW wind project in Benton County, IN, according to Berkeley Lab’s queue data file. The filing names bus in Cayuga substation on north side of plant as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of April 1, 2019.
| Queue ID | J515 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | bus in Cayuga substation on north side of plant |
| Point of interconnection | 345 kV bus in Cayuga substation on north side of plant |
| County | Benton |
| State | IN |
| Voltage | 345 kV |
| Capacity | 400 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Proposed online date | 2019-04-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Benton, IN: 16 requests in the MISO queue, 8 active totaling 960 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Cluster | DPP-2016-FEB Central |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | GIA |
| Queue date | 2015-11-16 |
| Interconnection agreement date | 2017-02-23 |
| Operational date | 2019-04-01 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.