Substation Scout

MISO request J4168

MISO queue ID J4168

Queue request J4168 was listed in the MISO interconnection queue at the end of 2025 as a 330 MW battery project in Goodhue County, MN, according to Berkeley Lab’s queue data file. The filing names NROC 3 to PR ISLD3 line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 3, 2028.

Queue IDJ4168
Project nameNot reported
Status (as published)Active
SubstationNROC 3 to PR ISLD3 line
Point of interconnectionNROC 3 (601039) to PR ISLD3 (601003) 345 kV line
CountyGoodhue
StateMN
Voltage345 kV
Capacity330 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-04-03
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Goodhue, MN: 29 requests in the MISO queue, 9 active totaling 1,956 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN STATES POWER COMPANY
ClusterDPP Cycle Pending West
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-03

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first