MISO request J416

MISO queue ID J416

Queue request J416 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Franklin County, IA, according to Berkeley Lab’s queue data file. The filing names Emery - Blackhawk (Section of MVP4) as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 15, 2017.

Queue IDJ416
Project nameNot reported
Status (as published)Operational
SubstationEmery - Blackhawk (Section of MVP4)
Point of interconnectionEmery - Blackhawk 345 kV (Section of MVP4)
CountyFranklin
StateIA
Voltage345 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2017-09-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Franklin, IA: 24 requests in the MISO queue, 12 active totaling 1,618 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2015-FEB West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2014-11-14
Interconnection agreement date2016-09-02
Operational date2017-09-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.