MISO request J4130
MISO queue ID J4130
Queue request J4130 was listed in the MISO interconnection queue at the end of 2025 as a 110 MW solar project in Pepin County, WI, according to Berkeley Lab’s queue data file. The filing names ALMA - ROCK ELM as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 1, 2030.
| Queue ID | J4130 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | ALMA - ROCK ELM |
| Point of interconnection | ALMA - ROCK ELM 161.0kV |
| County | Pepin |
| State | WI |
| Voltage | 161 kV |
| Capacity | 110 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2030-12-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Pepin, WI: 1 request in the MISO queue, 1 active totaling 110 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | DAIRYLAND POWER COOPERATIVE |
|---|---|
| Cluster | DPP Cycle Pending West |
| Interconnection service | NRIS |
| Project type | Generation |
| Queue date | 2025-10-01 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.