MISO request J4101
MISO queue ID J4101
Queue request J4101 was listed in the MISO interconnection queue at the end of 2025 as a 71 MW solar project in Jefferson County, WI, according to Berkeley Lab’s queue data file. The filing names University (UWW) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of March 31, 2028.
| Queue ID | J4101 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | University (UWW) |
| Point of interconnection | University (UWW) |
| County | Jefferson |
| State | WI |
| Voltage | Not reported |
| Capacity | 71 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2028-03-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Jefferson, WI: 8 requests in the MISO queue, 5 active totaling 362.8 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | AMERICAN TRANSMISSION COMPANY |
|---|---|
| Cluster | DPP Cycle Pending East (ATC) |
| Interconnection service | NRIS |
| Project type | Generation |
| Queue date | 2025-10-07 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.