Substation Scout

MISO request J4058

MISO queue ID J4058

Queue request J4058 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW battery project in Huron County, MI, according to Berkeley Lab’s queue data file. The filing names WYATT as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2028.

Queue IDJ4058
Project nameNot reported
Status (as published)Active
SubstationWYATT
Point of interconnectionWYATT
CountyHuron
StateMI
VoltageNot reported
Capacity250 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Huron, MI: 41 requests in the MISO queue, 29 active totaling 4,917.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC
ClusterDPP Cycle Pending East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-08-22

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first