Substation Scout

MISO request J4046

MISO queue ID J4046

Queue request J4046 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW solar project in Attala County, MS, according to Berkeley Lab’s queue data file. The filing names CONEHOMA CREEK - CARTHAGE (MS) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of January 1, 2030.

Queue IDJ4046
Project nameNot reported
Status (as published)Active
SubstationCONEHOMA CREEK - CARTHAGE (MS)
Point of interconnectionCONEHOMA CREEK - CARTHAGE (MS) 115.0kV
CountyAttala
StateMS
Voltage115 kV
Capacity100 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-01-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Attala, MS: 2 requests in the MISO queue, 2 active totaling 300 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY MISSISSIPPI, LLC.
ClusterDPP Cycle Pending South
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-07-17

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.