Queue request J3911 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW solar project in Louisa County, IA, according to Berkeley Lab’s queue data file. The filing names SUB 93 LOUISA - SUB T HASKINS as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2030.

Queue IDJ3911
Project nameNot reported
Status (as published)Active
SubstationSUB 93 LOUISA - SUB T HASKINS
Point of interconnectionSUB 93 LOUISA - SUB T HASKINS 345.0kV
CountyLouisa
StateIA
Voltage345 kV
Capacity250 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

SUB 93 LOUISA - SUB T HASKINS substation: 2 requests in the MISO queue, 2 active totaling 450 MW.

Queue IDProjectMWResourceStatus
J3725Not reported200SolarActive

Louisa, IA: 4 requests in the MISO queue, 3 active totaling 614.1 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMIDAMERICAN ENERGY CO.
ClusterDPP Cycle Pending West
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-02-25

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first