Queue request J390 was listed in the MISO interconnection queue at the end of 2025 as a 711 MW gas project in Rock County, WI, according to Berkeley Lab’s queue data file. The filing names Paddock - Rockdale line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of November 15, 2017.

Queue IDJ390
Project nameNot reported
Status (as published)Operational
SubstationPaddock - Rockdale line
Point of interconnectionPaddock - Rockdale 345 kV line
CountyRock
StateWI
Voltage345 kV
Capacity711 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2017-11-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Rock, WI: 26 requests in the MISO queue, 15 active totaling 2,594.1 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2015-FEB East (ATC)
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2014-09-15
Interconnection agreement date2017-04-21
Operational date2017-11-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first