Queue request J3874 was listed in the MISO interconnection queue at the end of 2025 as a 770 MW gas project in Union County, AR, according to Berkeley Lab’s queue data file. The filing names EL DORADO EHV as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 1, 2028.

Queue IDJ3874
Project nameNot reported
Status (as published)Active
SubstationEL DORADO EHV
Point of interconnectionEL DORADO EHV
CountyUnion
StateAR
VoltageNot reported
Capacity770 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2028-11-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Union, AR: 17 requests in the MISO queue, 7 active totaling 3,140 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY ARKANSAS
ClusterDPP Cycle Pending South
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-12-19

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first