Substation Scout

MISO request J340

MISO queue ID J340

Queue request J340 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW wind project in Huron County, MI, according to Berkeley Lab’s queue data file. The filing names Harvest Wind Tap on Cosmo-Bad Axe line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 1, 2016.

Queue IDJ340
Project nameNot reported
Status (as published)Operational
SubstationHarvest Wind Tap on Cosmo-Bad Axe line
Point of interconnectionHarvest Wind Tap on Cosmo-Bad Axe 120 kv line
CountyHuron
StateMI
Voltage120 kV
Capacity100 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2016-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Huron, MI: 41 requests in the MISO queue, 29 active totaling 4,917.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2014-AUG East (ITC)
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2014-05-16
Interconnection agreement date2015-08-26
Operational date2016-09-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.