Substation Scout

MISO request J3213

MISO queue ID J3213

Queue request J3213 was listed in the MISO interconnection queue at the end of 2025 as a 51 MW gas project in Hennepin County, MN, according to Berkeley Lab’s queue data file. The filing names Riverside Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2026.

Queue IDJ3213
Project nameNot reported
Status (as published)Active
SubstationRiverside Substation
Point of interconnectionRiverside 115kV Substation
CountyHennepin
StateMN
Voltage115 kV
Capacity51 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2026-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Hennepin, MN: 3 requests in the MISO queue, 2 active totaling 561 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN STATES POWER COMPANY
ClusterDPP-2022 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.