Queue request J3185 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW hybrid project in Effingham County, IL, according to Berkeley Lab’s queue data file. The filing names Effingham - Newton (4EFFINGHM -4NEWTON ) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of February 1, 2027.

Queue IDJ3185
Project nameNot reported
Status (as published)Active
SubstationEffingham - Newton (4EFFINGHM -4NEWTON )
Point of interconnectionEffingham - Newton 138KV (4EFFINGHM 347025 -4NEWTON 347831)
CountyEffingham
StateIL
Voltage138 kV
Capacity150 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2027-02-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Effingham, IL: 1 request in the MISO queue, 1 active totaling 150 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP-2022 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-15
Components (hybrid)Solar 150 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.