MISO queue ID J3107

Queue request J3107 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW solar project in Johnson County, IA, according to Berkeley Lab’s queue data file. The filing names Enron Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 1, 2025.

Queue IDJ3107
Project nameNot reported
Status (as published)Active
SubstationEnron Substation
Point of interconnectionEnron Substation
CountyJohnson
StateIA
VoltageNot reported
Capacity150 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2025-08-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Johnson, IA: 7 requests in the MISO queue, 3 active totaling 153.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMIDAMERICAN ENERGY CO.
ClusterDPP-2022 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2025-10-23

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first