MISO request J2885

MISO queue ID J2885

Queue request J2885 was listed in the MISO interconnection queue at the end of 2025 as a 130 MW solar project in Red Lake County, MN, according to Berkeley Lab’s queue data file. The filing names Plummer Pipe as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of January 10, 2025.

Queue IDJ2885
Project nameNot reported
Status (as published)Active
SubstationPlummer Pipe
Point of interconnectionPlummer Pipe
CountyRed Lake
StateMN
VoltageNot reported
Capacity130 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2025-01-10
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Red Lake, MN: 2 requests in the MISO queue, 2 active totaling 134.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOTTER TAIL POWER COMPANY
ClusterDPP-2022 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.