Substation Scout

MISO request J2614

MISO queue ID J2614

Queue request J2614 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Henry County, IL, according to Berkeley Lab’s queue data file. The filing names Mercer as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 30, 2026.

Queue IDJ2614
Project nameNot reported
Status (as published)Active
SubstationMercer
Point of interconnectionMercer 161kV
CountyHenry
StateIL
Voltage161 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2026-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Henry, IL: 8 requests in the MISO queue, 3 active totaling 700 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
ClusterDPP-2022 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first