Substation Scout

MISO request J2423

MISO queue ID J2423

Queue request J2423 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW battery project in Columbia County, WI, according to Berkeley Lab’s queue data file. The filing names Columbia-North Madison as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2027.

Queue IDJ2423
Project nameNot reported
Status (as published)Active
SubstationColumbia-North Madison
Point of interconnectionColumbia-North Madison 345kV
CountyColumbia
StateWI
Voltage345 kV
Capacity300 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2027-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Columbia, WI: 33 requests in the MISO queue, 13 active totaling 2,565.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMERICAN TRANSMISSION COMPANY
ClusterDPP-2022 East (ATC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-13

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first