MISO request J174

MISO queue ID J174

Queue request J174 was listed in the MISO interconnection queue at the end of 2025 as a 43.8 MW gas project in Jefferson County, WI, according to Berkeley Lab’s queue data file. The filing names ATC University Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 30, 2011.

Queue IDJ174
Project nameNot reported
Status (as published)Operational
SubstationATC University Substation
Point of interconnectionATC University Substation
CountyJefferson
StateWI
VoltageNot reported
Capacity43.8 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2011-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Jefferson, WI: 8 requests in the MISO queue, 5 active totaling 362.8 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Feasibility
Queue date2010-11-12
Interconnection agreement date2011-08-08
Operational date2011-09-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.