Substation Scout

MISO request J1437

MISO queue ID J1437

Queue request J1437 was listed in the MISO interconnection queue at the end of 2025 as a 180 MW wind project in Carroll County, AR, according to Berkeley Lab’s queue data file. The filing names AECC Dry Creek Switchyard Station as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 1, 2024.

Queue IDJ1437
Project nameNot reported
Status (as published)Active
SubstationAECC Dry Creek Switchyard Station
Point of interconnectionAECC Dry Creek 161kV Switchyard Station
CountyCarroll
StateAR
Voltage161 kV
Capacity180 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2024-05-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Carroll, AR: 2 requests in the MISO queue, 1 active totaling 180 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityARKANSAS ELECTRIC COOPERATIVE CORPORATION
ClusterDPP-2019 South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue date2019-04-29
Interconnection agreement date2021-12-22

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first