Substation Scout

MISO request J069

MISO queue ID J069

Queue request J069 was listed in the MISO interconnection queue at the end of 2025 as a 3.9 MW hydro project in Perry County, IN, according to Berkeley Lab’s queue data file. The filing names Tell City - Cloverpoint as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 30, 2011.

Queue IDJ069
Project nameNot reported
Status (as published)Operational
SubstationTell City - Cloverpoint
Point of interconnectionTell City - Cloverpoint 138 kV
CountyPerry
StateIN
Voltage138 kV
Capacity3.9 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Proposed online date2011-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Perry, IN: 2 requests in the MISO queue, 2 active totaling 87.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2009-NOV Indiana
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2009-09-28
Interconnection agreement date2011-03-07
Operational date2011-09-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.