Substation Scout

MISO request G889

MISO queue ID G889

Queue request G889 was listed in the MISO interconnection queue at the end of 2025 as a 59.4 MW wind project in Huron County, MI, according to Berkeley Lab’s queue data file. The filing names ITC Cosmo Tap (Bad Axe - Arrowhead) as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of February 28, 2008.

Queue IDG889
Project nameNot reported
Status (as published)Operational
SubstationITC Cosmo Tap (Bad Axe - Arrowhead)
Point of interconnectionITC Cosmo Tap (Bad Axe - Arrowhead) 120 kV
CountyHuron
StateMI
Voltage120 kV
Capacity59.4 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2008-02-28
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Huron, MI: 41 requests in the MISO queue, 29 active totaling 4,917.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2008-NOV MI
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2007-10-18
Interconnection agreement date2012-07-05
Operational date2008-02-28

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.