Queue request G876 was listed in the MISO interconnection queue at the end of 2025 as a 25 MW coal project in Mclean County, ND, according to Berkeley Lab’s queue data file. The filing names GRE Coal Creek Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 31, 2009.

Queue IDG876
Project nameNot reported
Status (as published)Operational
SubstationGRE Coal Creek Substation
Point of interconnectionGRE Coal Creek 230 kV Substation
CountyMclean
StateND
Voltage230 kV
Capacity25 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Proposed online date2009-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

GRE Coal Creek Substation substation: 3 requests in the MISO queue, 2 active totaling 65 MW.

Queue IDProjectMWResourceStatus
G877Not reported40CoalOperational
J212Not reported600WindWithdrawn

Mclean, ND: 4 requests in the MISO queue, 2 active totaling 65 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2008-NOV ND
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2007-10-09
Interconnection agreement date2009-10-02
Operational date2009-12-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first