Queue request G580 was listed in the MISO interconnection queue at the end of 2025 as a 50 MW coal project in Jefferson County, OH, according to Berkeley Lab’s queue data file. The filing names WH Sammis Plant Unit 7 as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 30, 2006.

Queue IDG580
Project nameNot reported
Status (as published)Operational
SubstationWH Sammis Plant Unit 7
Point of interconnectionWH Sammis Plant Unit 7
CountyJefferson
StateOH
VoltageNot reported
Capacity50 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Proposed online date2006-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Jefferson, OH: 2 requests in the MISO queue, 2 active totaling 100 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Feasibility
Queue date2005-12-23
Interconnection agreement date2007-06-21
Operational date2006-09-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first