Substation Scout

MISO request G518

MISO queue ID G518

Queue request G518 was listed in the MISO interconnection queue at the end of 2025 as a 8 MW wind project in Jackson County, MN, according to Berkeley Lab’s queue data file. The filing names Miloma - Round Lake as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of October 1, 2007.

Queue IDG518
Project nameNot reported
Status (as published)Operational
SubstationMiloma - Round Lake
Point of interconnectionMiloma - Round Lake 69 kV
CountyJackson
StateMN
Voltage69 kV
Capacity8 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2007-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Jackson, MN: 29 requests in the MISO queue, 10 active totaling 837 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterGS4
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2005-05-02
Interconnection agreement date2006-09-27
Operational date2007-10-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.