Substation Scout

MISO request G409

MISO queue ID G409

Queue request G409 was listed in the MISO interconnection queue at the end of 2025 as a 2 MW project in Dawson County, MT, according to Berkeley Lab’s queue data file. The filing names Glendive as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 1, 2007.

Queue IDG409
Project nameNot reported
Status (as published)Operational
SubstationGlendive
Point of interconnectionGlendive
CountyDawson
StateMT
VoltageNot reported
Capacity2 MW
Resource (as published)Diesel
Resource categoryOther (normalized for filtering)
Proposed online date2007-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Dawson, MT: 2 requests in the MISO queue, 2 active totaling 47 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2004-02-23
Interconnection agreement date2004-07-13
Operational date2007-12-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first