Substation Scout

MISO request G396

MISO queue ID G396

Queue request G396 was listed in the MISO interconnection queue at the end of 2025 as a 2 MW project in Grant County, SD, according to Berkeley Lab’s queue data file. The filing names Milbank as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of July 1, 2004.

Queue IDG396
Project nameNot reported
Status (as published)Operational
SubstationMilbank
Point of interconnectionMilbank 41.6kV
CountyGrant
StateSD
Voltage41.6 kV
Capacity2 MW
Resource (as published)Diesel
Resource categoryOther (normalized for filtering)
Proposed online date2004-07-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Grant, SD: 24 requests in the MISO queue, 6 active totaling 856.8 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG396 G396
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2004-01-13
Interconnection agreement date2004-06-03
Operational date2004-07-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.