MISO request G380
MISO queue ID G380
Queue request G380 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW wind project in Pierce County, ND, according to Berkeley Lab’s queue data file. The filing names Rugby Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 1, 2005.
| Queue ID | G380 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Rugby Substation |
| Point of interconnection | Rugby 115kV Substation |
| County | Pierce |
| State | ND |
| Voltage | 115 kV |
| Capacity | 150 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Proposed online date | 2005-12-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Pierce, ND: 1 request in the MISO queue, 1 active totaling 150 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Cluster | G380 G380 |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Network Upgrade |
| Queue date | 2003-11-21 |
| Interconnection agreement date | 2006-04-11 |
| Operational date | 2005-12-01 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.