Substation Scout

MISO request G374

MISO queue ID G374

Queue request G374 was listed in the MISO interconnection queue at the end of 2025 as a 6 MW wind project in Nobles County, MN, according to Berkeley Lab’s queue data file. The filing names Rushmore Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of May 1, 2005.

Queue IDG374
Project nameNot reported
Status (as published)Operational
SubstationRushmore Substation
Point of interconnectionRushmore 69kV Substation
CountyNobles
StateMN
Voltage69 kV
Capacity6 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2005-05-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Nobles, MN: 25 requests in the MISO queue, 12 active totaling 1,409.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG374 G374
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2003-11-13
Interconnection agreement date2005-05-27
Operational date2005-05-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first