Substation Scout

MISO request G017

MISO queue ID G017

Queue request G017 was listed in the MISO interconnection queue at the end of 2025 as a 174 MW gas project in Trimble County, KY, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2004.

Queue IDG017
Project nameNot reported
Status (as published)Active
SubstationNot reported
Point of interconnectionNot reported
CountyTrimble
StateKY
VoltageNot reported
Capacity174 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2004-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Trimble, KY: 7 requests in the MISO queue, 7 active totaling 1,794 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Queue date1999-12-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first