Substation Scout

Woodruff, AR interconnection queue

1 active project totaling 130 MW in the MISO queue, plus 4 with terminal status (shown grayed).

1active projects
130active MW
5total filed
Queue IDProjectkVMWResourceStatus
J3308 Not reported 161 180 Solar Withdrawn
J3253 Not reported n/r 150 Solar Withdrawn
J2801 Not reported 161 130 Solar Active
J2630 Not reported 115 100 Solar Withdrawn
J894 Not reported 161 45 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first