Waupaca, WI interconnection queue

1 active project totaling 300 MW in the MISO queue, plus 2 with terminal status (shown grayed).

1active projects
300active MW
3total filed
Queue IDProjectkVMWResourceStatus
J1513 Not reported n/r 300 Solar Active
G415 Not reported n/r 25 Other Withdrawn
J1486 Not reported 138 2.5 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.