Substation Scout

Watonwan, MN interconnection queue

1 active project totaling 1,000 MW in the MISO queue, plus 7 with terminal status (shown grayed).

1active projects
1,000active MW
8total filed
Queue IDProjectkVMWResourceStatus
J4161 Not reported 345 1,000 Solar Active
J3524 Not reported 345 300 Solar Withdrawn
J3823 Not reported 345 300 Solar Withdrawn
H019 Not reported n/r 150 Wind Withdrawn
H044 Not reported 69 75 Wind Withdrawn
G768 Not reported 69 50 Wind Withdrawn
G411 Not reported n/r 19.8 Wind Withdrawn
J032 Not reported 69 4.9 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.