Warren, MO interconnection queue

3 active projects totaling 639 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3active projects
639active MW
5total filed
Queue IDProjectkVMWResourceStatus
J976 Not reported 345 300 Solar Active
J2806 Not reported 161 200 Solar Active
J817 Not reported 161 139 Solar Operational
J2584 Not reported 161 100 Battery Withdrawn
J1039 Not reported 345 50 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.