Wadena, MN interconnection queue

1 active project totaling 150 MW in the MISO queue, plus 4 with terminal status (shown grayed).

1active projects
150active MW
5total filed
Queue IDProjectkVMWResourceStatus
J1221 Not reported 230 150 Solar Active
J2433 Not reported 230 150 Solar Withdrawn
J702 Not reported n/r 100 Solar Withdrawn
J1597 Not reported 230 75 Solar Withdrawn
J1230 Not reported 230 40 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.