Stevens, MN interconnection queue
2 active projects totaling 460 MW in the MISO queue, plus 7 with terminal status (shown grayed).
2active projects
460active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J2624 | Not reported | 345 | 450 | Battery | Withdrawn |
| G805 | Not reported | 115 | 300 | Wind | Withdrawn |
| J3669 | Not reported | 345 | 300 | Solar | Active |
| J2608 | Not reported | 115 | 160 | Solar | Active |
| G555 | Not reported | 115 | 100 | Wind | Withdrawn |
| G737 | Not reported | 115 | 100 | Wind | Withdrawn |
| G638 | Not reported | 41 | 20 | Wind | Withdrawn |
| G644 | Not reported | 115 | 20 | Wind | Withdrawn |
| G777 | Not reported | n/r | 20 | Wind | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.