St. Clair, IL interconnection queue
4 active projects totaling 645 MW in the MISO queue, plus 7 with terminal status (shown grayed).
4active projects
645active MW
11total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J2697 | Not reported | 345 | 500 | Hybrid | Withdrawn |
| J3200 | Not reported | 345 | 250 | Battery | Withdrawn |
| J2204 | Not reported | n/r | 200 | Battery | Withdrawn |
| J2998 | Not reported | 138 | 200 | Battery | Active |
| J2645 | Not reported | 138 | 199 | Solar | Withdrawn |
| J1311 | Not reported | 138 | 150 | Solar | Active |
| J3297 | Not reported | n/r | 150 | Battery | Withdrawn |
| S1077 | Surplus | n/r | 150 | Battery | Active |
| J3184 | Not reported | 138 | 145 | Hybrid | Active |
| J3011 | Not reported | 345 | 100 | Battery | Withdrawn |
| J3069 | Not reported | 138 | 70 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.