Red River Parish, LA interconnection queue

2 active projects totaling 280 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2active projects
280active MW
4total filed
Queue IDProjectkVMWResourceStatus
J1452 Not reported 138 200 Solar Withdrawn
J2526 Not reported 230 200 Solar Active
J2489 Not reported 230 140 Battery Withdrawn
J2819 Not reported 115 80 Hybrid Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.