Poinsett, AR interconnection queue
2 active projects totaling 240 MW in the MISO queue, plus 9 with terminal status (shown grayed).
2active projects
240active MW
11total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J2386 | Not reported | 161 | 300 | Solar | Withdrawn |
| J3569 | Not reported | 161 | 300 | Solar | Withdrawn |
| J3571 | Not reported | 161 | 250 | Solar | Withdrawn |
| J3373 | Not reported | 161 | 200 | Solar | Withdrawn |
| J3969 | Not reported | n/r | 196 | Solar | Withdrawn |
| J3536 | Not reported | 161 | 190 | Hybrid | Withdrawn |
| J2928 | Not reported | 161 | 160 | Solar | Withdrawn |
| J4174 | Not reported | n/r | 140 | Battery | Active |
| J2773 | Not reported | 161 | 100 | Hybrid | Active |
| J948 | Not reported | 161 | 100 | Solar | Withdrawn |
| J2521 | Not reported | 161 | 50 | Battery | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.