Mercer, IL interconnection queue

2 active projects totaling 445.6 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2active projects
445.6active MW
4total filed
Queue IDProjectkVMWResourceStatus
J3750 Not reported 345 250 Wind Active
G569 Not reported n/r 200 Wind Withdrawn
J3801 Not reported 345 195.6 Solar Active
J2713 Not reported n/r 47.6 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.