Mccracken, KY interconnection queue
1 active project totaling 60 MW in the MISO queue, plus 3 with terminal status (shown grayed).
1active projects
60active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| G070 | Not reported | n/r | 900 | Other | Withdrawn |
| J2547 | Not reported | 161 | 150 | Solar | Withdrawn |
| J2548 | Not reported | 161 | 75 | Battery | Withdrawn |
| J1649 | Not reported | 69 | 60 | Solar | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.