Marshall, MN interconnection queue

2 active projects totaling 150 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2active projects
150active MW
4total filed
Queue IDProjectkVMWResourceStatus
G600 Not reported 115 110 Wind Withdrawn
G968 Not reported 115 100 Wind Withdrawn
J4009 Not reported 115 80 Solar Active
J1575 Not reported 115 70 Wind Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.