Substation Scout

Lyon, MN interconnection queue

7 active projects totaling 1,203.5 MW in the MISO queue, plus 19 with terminal status (shown grayed).

7active projects
1,203.5active MW
26total filed
Queue IDProjectkVMWResourceStatus
J131 Not reported n/r 300 Gas Withdrawn
G841 Not reported n/r 250 Wind Withdrawn
G842 Not reported 115 250 Wind Withdrawn
J3326 Not reported n/r 250 Wind Active
J3346 Not reported n/r 250 Wind Withdrawn
J3894 Not reported 345 250 Battery Active
J3021 Not reported 115 235 Solar Active
H081 Not reported 345 201 Wind Operational
H083 Not reported 345 200 Wind Withdrawn
J1395 Not reported 345 200 Solar Withdrawn
J254 Not reported 345 200 Wind Withdrawn
J3749 Not reported n/r 200 Wind Active
J739 Not reported 345 200 Wind Withdrawn
J3020 Not reported 115 165 Wind Withdrawn
G520 Not reported 115 150 Wind Withdrawn
J198 Not reported 115 99 Wind Withdrawn
J400 Not reported 115 62.5 Solar Operational
J295 Not reported 69 50 Gas Withdrawn
J305 Not reported n/r 50 Solar Withdrawn
J391 Not reported n/r 50 Gas Withdrawn
J803 Not reported 69 32.5 Solar Withdrawn
J330 Not reported 69 24.8 Solar Withdrawn
G489 Not reported 115 20 Wind Withdrawn
J454 Not reported n/r 18.9 Wind Withdrawn
G177 Not reported n/r 5 Other Active
J155 Not reported 69 4.9 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.