1 active project totaling 135 MW in the MISO queue, plus 2 with terminal status (shown grayed).

1active projects
135active MW
3total filed
Queue IDProjectkVMWResourceStatus
H023 Not reported n/r 135 Gas Withdrawn
H037 Not reported n/r 135 Gas Active
G754 Not reported 138 50 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.