Lorain, OH interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
G942 Not reported 345 24 Coal Withdrawn
J173 Not reported 69 19.2 Other Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.