Lincoln, SD interconnection queue

1 active project totaling 120 MW in the MISO queue, plus 1 with terminal status (shown grayed).

1active projects
120active MW
2total filed
Queue IDProjectkVMWResourceStatus
J744 Not reported n/r 400 Wind Withdrawn
J3546 Not reported 115 120 Wind Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.