Lafayette Parish, LA interconnection queue

4 active projects totaling 1,042.7 MW in the MISO queue, plus 3 with terminal status (shown grayed).

4active projects
1,042.7active MW
7total filed
Queue IDProjectkVMWResourceStatus
J2888 Not reported 500 500 Solar Withdrawn
J4110 Not reported 230 400 Gas Active
J4098 Not reported 230 300 Battery Active
J2791 Not reported 69 262.7 Gas Active
J1818 Not reported 69 80 Solar Active
J645 Not reported n/r 48.8 Solar Withdrawn
J710 Not reported 69 20 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.